  • New Wastewater Treatment Plant!

Photos of Building Progress

North Catwalk.JPG
previous next
This long run of platform is the bottom form for the Large catwalk that serve as access to much of the mechanical equipment that will be in the basins as well as sit over the Effluent Filter and UV channel that will be on the backside of the sequencing batch reactor and Aerobic Digester.
Control Building
The Pad for the Blower were poured in place.
Catwalks
Generator Pad
Electrical Control Room
Control Building
Control Building
Control Building
SBR
SBR Exterior
Control Building Exterior
Control Building Roof
SBR Walls
Generator Pad
HVAC
Control Building
SBR
SBR
Biosolids Room
Control Building
Control Building
IMG_1771.jpeg
Control Building
Equalization Basin
Generator pad
Control Building
Blower room with paint on the walls and pedestals ready for the equipment installation.
Operator Room
last runs of piping from one structure to another getting placed.
The last sections of the sequencing batch reactor walls to be pour are getting formed in.
SBR
Catwalks
Control Building
Overview
SBR
Headworks Rebar.jpg
Lab.jpg
FKC.jpg
EQ Basin Walls.jpg
Headworks Forms.jpg
Conduit Runs.jpg
EQ Basin Walls 2.jpg
AD Catwalk.jpg
Blower Piping.jpg
Splitter Box.jpg
Catwalks.JPG
Biosolids Holding.JPG
Blower Room.JPG
EQ Basin Completed.jpg
Headworks Splitter Box.JPG
North Catwalk.JPG