Photos of Building Progress

Control Building
previous next
The Control Building is framed in with roofing, trim, and siding getting installed.
Control Building
The Pad for the Blower were poured in place.
Catwalks
Generator Pad
Electrical Control Room
Control Building
Control Building
Control Building
SBR
SBR Exterior
Control Building Exterior
Control Building Roof
SBR Walls
Generator Pad
HVAC
Control Building
SBR
SBR
Biosolids Room
Control Building
Control Building
IMG_1771.jpeg
Control Building
Equalization Basin
Generator pad
Control Building
Blower room with paint on the walls and pedestals ready for the equipment installation.
Operator Room
last runs of piping from one structure to another getting placed.
The last sections of the sequencing batch reactor walls to be pour are getting formed in.
SBR
Catwalks
Control Building
Overview
SBR