New Police Station and Police Bond Updates

Share New Police Station and Police Bond Updates on Facebook Share New Police Station and Police Bond Updates on Twitter Share New Police Station and Police Bond Updates on Linkedin Email New Police Station and Police Bond Updates link

Building a new Molalla Police Station

In November of 2023 voters within the City of Molalla approved a bond levy to construct a new Police Station by a slim margin. Although the process for moving forward on this project has reached a fervent pace recently, the project really began in 2012 when former Police Chief Rod Lucich began to express the need for a new station. The City began to put money away for this endeavor and in 2015 the City purchased the old Bowling Alley property on Grange Avenue in 2021.


Some of you will remember that the Bowling Alley had been abandoned and was in a state of decay since about 2017. The City held an auction of left behind Bowling Alley equipment in 2022. We saved two items from the old building: bowling pins and the bowling alley lanes. Bowling pins have been decorated and sold to raise funding for our park system and the old alleys have been safely stored and will be incorporated into the new Police Station.


Where does that leave us today?

Design and development of final plans for the new Police Facility are almost complete. The City Council approved an early procurement of masonry, electrical, mechanical, steel, and other long-term items so that we are ready when these items are needed. Architects are working toward building permitting and these applications have been filed with the Clackamas County Building Department.


Be looking for groundbreaking in mid-July this summer!



If you have questions, please let us know by asking your question here. Many times, others have the same questions, and we can provide answers to all of you.
Or you can ask a question by e-mailing the city manager.(External link)


Dan Huff

Molalla City Manager

Building a new Molalla Police Station

In November of 2023 voters within the City of Molalla approved a bond levy to construct a new Police Station by a slim margin. Although the process for moving forward on this project has reached a fervent pace recently, the project really began in 2012 when former Police Chief Rod Lucich began to express the need for a new station. The City began to put money away for this endeavor and in 2015 the City purchased the old Bowling Alley property on Grange Avenue in 2021.


Some of you will remember that the Bowling Alley had been abandoned and was in a state of decay since about 2017. The City held an auction of left behind Bowling Alley equipment in 2022. We saved two items from the old building: bowling pins and the bowling alley lanes. Bowling pins have been decorated and sold to raise funding for our park system and the old alleys have been safely stored and will be incorporated into the new Police Station.


Where does that leave us today?

Design and development of final plans for the new Police Facility are almost complete. The City Council approved an early procurement of masonry, electrical, mechanical, steel, and other long-term items so that we are ready when these items are needed. Architects are working toward building permitting and these applications have been filed with the Clackamas County Building Department.


Be looking for groundbreaking in mid-July this summer!



If you have questions, please let us know by asking your question here. Many times, others have the same questions, and we can provide answers to all of you.
Or you can ask a question by e-mailing the city manager.(External link)


Dan Huff

Molalla City Manager

  • Construction Progress Photos April 17, 2025

    Share Construction Progress Photos April 17, 2025 on Facebook Share Construction Progress Photos April 17, 2025 on Twitter Share Construction Progress Photos April 17, 2025 on Linkedin Email Construction Progress Photos April 17, 2025 link
    17 Apr 2025

    The new Police Department continues to meet construction deadlines on is on budget! It is exciting to watch the project develop and see the weekly changes.



  • Construction Progress Updates March 13, 2025

    Share Construction Progress Updates March 13, 2025 on Facebook Share Construction Progress Updates March 13, 2025 on Twitter Share Construction Progress Updates March 13, 2025 on Linkedin Email Construction Progress Updates March 13, 2025 link
    13 Mar 2025

    The new Police Department construction is continuing to follow expected time lines.


  • Progress updates

    Share Progress updates on Facebook Share Progress updates on Twitter Share Progress updates on Linkedin Email Progress updates link
    27 Feb 2025

    Construction of the new police department continues on time and on budget!



  • More Progress on the New Police Station

    Share More Progress on the New Police Station on Facebook Share More Progress on the New Police Station on Twitter Share More Progress on the New Police Station on Linkedin Email More Progress on the New Police Station link
    21 Feb 2025

    With the roofing placed on the new police station it finally looks like a real building. This is an exciting milestone and we are looking forward to the completion of the interior.


  • Police Station Construction Update Photos

    Share Police Station Construction Update Photos on Facebook Share Police Station Construction Update Photos on Twitter Share Police Station Construction Update Photos on Linkedin Email Police Station Construction Update Photos link
    18 Feb 2025

    Today, February 18, 2025, P&C lifted and set in place approximately 16 CLT (cross laminated timber) panels at the high roof of the project. The city, police department, owner’s rep, Mackenzie and the structural engineers were present to witness the delivery and installation and took notes on the process. The weather was cooperative for such an important crane operation and all safety protocols were in place for the project team to witness.



  • Construction Progress Photos

    Share Construction Progress Photos on Facebook Share Construction Progress Photos on Twitter Share Construction Progress Photos on Linkedin Email Construction Progress Photos link
    18 Feb 2025

    Updated construction photos. It's beginning to look like a real building and the roof should be on very soon!










  • Job Site Camera

    Share Job Site Camera on Facebook Share Job Site Camera on Twitter Share Job Site Camera on Linkedin Email Job Site Camera link
    04 Sep 2024

    CLICK BELOW FOR A JOB-SITE CAMERA

    (External link)


    P&C Construction(External link) has broken ground on the new Molalla Police Department(External link) read all about it;

    https://djcoregon.com/.../on-the-boards-molalla-police.../(External link)

  • Facility Update 08.21.24

    Share Facility Update 08.21.24 on Facebook Share Facility Update 08.21.24 on Twitter Share Facility Update 08.21.24 on Linkedin Email Facility Update 08.21.24 link
    21 Aug 2024

    On August 14, 2024 the Molalla City Council approved a final amendment to the construction contract with P&C Construction that brought the total and final contract GMP amount to $16,877,864. This is in line with our planning and site work and utilities have already begun! Start up activities such as the groundbreaking ceremony, site security, job trailer, site trenching for utilities and footings, survey and various inspections are moving along and each week the owner, architect and contractor meet on site to review progress and collaborate. The project is on target to be complete by the end of 2025.



  • Ground Breaking!

    Share Ground Breaking! on Facebook Share Ground Breaking! on Twitter Share Ground Breaking! on Linkedin Email Ground Breaking! link
    09 Aug 2024

    The City of Molalla broke ground on a new police station last Friday, August 2, 2024. City officials and police staff celebrated with community members at the groundbreaking ceremony.

    The new station will be Molalla’s first dedicated police facility and will function as an emergency operations center to coordinate public safety crisis response activities. The project team includes Mackenzie and P&C Construction.

    We expect the new station to open in late 2025.


  • City Council Report of New Police Station February 28, 2024

    Share City Council Report of New Police Station February 28, 2024 on Facebook Share City Council Report of New Police Station February 28, 2024 on Twitter Share City Council Report of New Police Station February 28, 2024 on Linkedin Email City Council Report of New Police Station February 28, 2024 link
    28 Feb 2024

    City of Molalla- New Police Facility

    CITY COUNCIL REPORT

    DATE: February 28, 2024

    REPORT: City Council Update on New Police Facility

    PREPARED BY: Joshua Dodson, Owner’s Rep./Project Manager


    1) Project Vitals: 1.6 acre site, 17,832 SF single story new police facility located at old

    bowling alley property off 150 Grange Ave., project funded by $16M bond plus other funding, Construction cost range is currently [$16.8-17.6M], construction complete by Fall 2025, full project team has been established. Total project cost is $22Million.


    2) Construction Guaranteed Maximum Price Budget: $17.3 Million GMP (Guaranteed Maximum Price)

    a) Pie Charts, overall budget, later GMP & contingency spend down tracking

    Click below to see the Early Work Agreement for May 2024
    City Council - Early Work Agreement - May 2024

    3) Scope/Design Updates:

    a) Design Update from Mackenzie

    “Since reengaging on the design following the election in late 2023 the Mackenzie design team has been diligently working advancing the building and site design with the goal of issuing an early design package for P&C to procure select long lead items (mechanical and electrical equipment) and begin weather sensitive construction activities during the summer months. The early work will include site grading, utilities, and building foundations. The team has been coordinating design related security requirements for the Police Department, site access and circulation, and other critical police operational needs.”

    -David Linton, Architect from Mackenzie


    4) Time:

    a) Milestones:

    • Quarter two 2024 Early Procurement Package
    • Summer/Fall 2024 Site grading, utilities and foundation work
    • Quarter four 2024 main building construction start
    • Quarter four 2025 project completion


    5) Construction Updates:

    a) Construction Updates from P&C Construction

    “Upon the bond approval/Notice to Proceed, P&C has worked along the side the design team providing costing and pricing support as the design continues to develop. P&C continues discussions with subcontractor partners on procurement time frames to coordinate proper early work or material ordering. P&C is actively working on a detailed Master Construction Schedule outlining critical path work scheduled for start in late summer along with a procurement schedule for other long lead items ensuring all materials are available in time for their construction related activities.“

    -Jason Bragg, P&C Construction


    6) Interesting Things/Challenges:

    a) Bowling alley lane re-use as public space benches, wall finishes, possible gun rail, and other options are being explored

    b) No concerning challenges or concerns with budget, scope, and time at this period of the project


    Demolished Site


    New Police Station Rendering


    Planning Meeting


    Site Demolition


    Bowling Alley Lane Storage


    Planning Meeting


Page last updated: 17 Apr 2025, 01:16 PM