Traffic Impacts for Public Projects
Stay informed with the public projects around town!
See below the map of the current project.
If you have any questions, feel free to reach out!
Section Street
10/02/2024 Update
Section Street has been paved and is awaiting striping.
Molalla Public Library parking lot has been repaved and striped.
9/12/2024 Update
Section Street has been excavated and is now being reconstructed.
Expected paving date(tentatively) September 23.
Molalla Public Library parking lot will be closed and repaved simultaneously.
Project has begun with potholing on Section Street.
Project to include demolition & rebuild/paving of Section street and surfacing of Molalla Public Library parking lot.
Paving projected to be completed end of September.
N. Molalla Ave. Paving Project
North Molalla Ave. street paving
Tentative Schedule:
May 28th - Grinding to start
May 29th/30th - Paving of N. Molalla from Heintz Street to Church Street.
allowing a week for asphalt to cure
June 11th - Striping
S. Molalla Ave. Waterline Project
Paving & Striping on S Molalla is now complete.
Section Street is expected to begin the Second week of August is the projected start date. However, start date could move.
Click on the map above for the project closure area.
See the project progress on the right.
S. MOLALLA AVE. WATERLINE TRAFFIC CONTROL PLAN HERE
PAVING UPDATES: | |
Striping of S Molalla Ave from 3rd Street to Molalla Forest Rd. will take place Thursday August 8th from 7AM to approx. 5PM. This will include installation of thermoplastic stop bars and crosswalk at all intersection within the project area. There’ll be temporary traffic detours during striping to allow point to dry, traffic delays are to be expected so please plan accordingly. |
They're making progress! Approximately 2700 LF of new waterline installed.
Ona Way Road Closures
10/02/2024 Update:
Street has been paved, sidewalks are being poured and awaiting striping on Ona Way.
9/12/2024 Update:
Curb and gutter has been poured, contractor to finish final grading in preparation for paving.
Continue to detour to S Molalla Forest Road.