Traffic Impacts for Public Projects

Share Traffic Impacts for Public Projects on Facebook Share Traffic Impacts for Public Projects on Twitter Share Traffic Impacts for Public Projects on Linkedin Email Traffic Impacts for Public Projects link

Stay informed with the public projects around town!

See below the map of the current project.
If you have any questions, feel free to reach out!

Stay informed with the public projects around town!

See below the map of the current project.
If you have any questions, feel free to reach out!

Share Section Street on Facebook Share Section Street on Twitter Share Section Street on Linkedin Email Section Street link

Section Street

3 months

10/02/2024 Update

Section Street has been paved and is awaiting striping.

Molalla Public Library parking lot has been repaved and striped.



9/12/2024 Update

Section Street has been excavated and is now being reconstructed.

Expected paving date(tentatively) September 23.

Molalla Public Library parking lot will be closed and repaved simultaneously. 



Project has begun with potholing on Section Street.

Project to include demolition & rebuild/paving of Section street and surfacing of Molalla Public Library parking lot.

Paving projected to be completed end of September.

Share N. Molalla Ave. Paving Project on Facebook Share N. Molalla Ave. Paving Project on Twitter Share N. Molalla Ave. Paving Project on Linkedin Email N. Molalla Ave. Paving Project link

N. Molalla Ave. Paving Project

3 months

North Molalla Ave. street paving

Tentative Schedule:

May 28th - Grinding to start

May 29th/30th - Paving of N. Molalla from Heintz Street to Church Street.
allowing a week for asphalt to cure

June 11th - Striping

See Update HERE

CLOSED: This map consultation has concluded.
Share S. Molalla Ave. Waterline Project on Facebook Share S. Molalla Ave. Waterline Project on Twitter Share S. Molalla Ave. Waterline Project on Linkedin Email S. Molalla Ave. Waterline Project link

S. Molalla Ave. Waterline Project

3 months

Paving & Striping on S Molalla is now complete.

  

Section Street is expected to begin the Second week of August is the projected start date. However, start date could move.  


Click on the map above for the project closure area.

See the project progress on the right.

S. MOLALLA AVE. WATERLINE TRAFFIC CONTROL PLAN HERE


PAVING UPDATES:

Striping of S Molalla Ave from 3rd Street to Molalla Forest Rd. will take place Thursday August 8th from 7AM to approx. 5PM. This will include installation of thermoplastic stop bars and crosswalk at all intersection within the project area. There’ll be temporary traffic detours during striping to allow point to dry, traffic delays are to be expected so please plan accordingly.





They're making progress! Approximately 2700 LF of new waterline installed.

CLOSED: This map consultation has concluded.
Share Ona Way Road Closures on Facebook Share Ona Way Road Closures on Twitter Share Ona Way Road Closures on Linkedin Email Ona Way Road Closures link

Ona Way Road Closures

7 months

10/02/2024 Update:

Street has been paved, sidewalks are being poured and awaiting striping on Ona Way.


9/12/2024 Update:

Curb and gutter has been poured, contractor to finish final grading in preparation for paving.

Continue to detour to S Molalla Forest Road. 

Ona Way Road Closure Report


Page last updated: 02 Oct 2024, 04:01 PM