ODOT, in partnership with the City of Molalla, is improving safety at the intersection of Oregon 213 and Toliver Road in Molalla by constructing a roundabout.
Roundabout construction begins July 6 with an intersection full closure
Intersection closure at OR 213 and Toliver Road July 6 to August 31
ODOT, in partnership with the City of Molalla, is improving safety at the intersection of OR 213 and Toliver Road in Molalla by constructing a roundabout.
Currently, the intersection of OR 213 and Toliver Road is controlled by stop signs on Toliver Road and has a high rate of crashes. A roundabout will improve safety by reducing sharp turns while also accommodating the type of traffic that uses it, including large vehicles like trucks, buses and agricultural equipment.
Constructing the roundabout requires widening the intersection at Toliver Road and replacing an existing culvert carrying Bear Creek under Oregon 213. The entire intersection will be excavated at one time, which will leave a hole in the roadway during construction. Because of this, all users will need to detour.
The intersection of OR 213 and Toliver Road will be closed July 6 to Aug. 31, 2023.
Local access to homes and businesses is open up to the work zone, but no traffic will be permitted through the intersection.
Un cierre total de la intersección de OR 213 y Toliver Road del 6 de julio al 31 de agosto de 2023.
La intersección estará totalmente cerrada a todo el tráfico, incluyendo personas caminando y andando en bicicleta. Toda la intersección será excavada a la vez, lo que dejará un agujero en el camino durante la construcción. Todos los viajeros deberán usar las rutas de desviación marcadas u otras rutas alternas.
Detour information
Through traffic on OR 213 can follow a signed detour using OR 211/Main Street and South Union Mills Road. We do not plan to use flaggers to direct traffic along detour routes during roundabout construction.
El tráfico que seguirá en OR 213 puede seguir una desviación señalizada usando OR211/Main Street y South Union Mills Road.
Eastbound traffic on Toliver Road bound for OR 213 can head north on South Dryland Road and turn right onto South Barnards Road, or head south on South Dryland Road and turn left onto OR 211/Main Street.
El tráfico con dirección Este en Toliver Road que se dirige a OR 213 puede dirigirse al Norte en South Dryland Road y dar vuelta a la derecha hacia South Barnards Road, o dirigirse hacia el Sur en South Dryland Road y dar vuelta a la izquierda hacia OR 211/Main Street.
Westbound traffic on Toliver Road bound for OR 213 can use Leroy Avenue and turn left onto OR 211/Main Street for OR 213 north, or turn right onto OR 211/Main Street for OR 213 south.
El tráfico hacia el Oeste en Toliver Road que se dirige a OR 213 puede usar Leroy Avenue y dar vuelta a la izquierda hacia OR 211/Main Street para OR 213 norte, o dar vuelta a la derecha hacia OR 211/Main Street para OR 213 sur.
Nighttime Noise
Those living or working in the area may hear noise from construction. A 24/7 nighttime noise hotline is be available for noise concerns: 503-276-7893