Project 21-06 Waterline 500 Block of W Main St - Complete!

This project was completed in July of 2022.

Project 21-06 was identified during a systemwide leak survey performed in 2021 when the failing line was identified and estimated to account for approximately 6% of the City's total water loss.

The project was initially budgeted at $245,000, but was delivered by City Staff for $215,000, a 12% cost savings. This project was entirely funded by grant proceeds from the American Rescue Plan Act (ARPA).