Project 20-04 Toliver Road Waterline - Complete!

CLOSED: This discussion has concluded.

This project was completed in May of 2022.

Project 20-04 is listed in the Molalla Water System Master Plan and the FY22-23 Capital Improvement Plan. The project replaced 1,100 feet of antiquated water main with a new 8-inch main to address the reliability of the water distribution system and to improve fire flows to the Elementary School, Wastewater Treatment Plant, and City Shops.

The initial cost estimate was $620,000, but City Staff was able to deliver the project under budget at $544,000, a 12% cost savings.